| Criterion
6.2.10 Buried Components
Criterion
text:
Solar
components and materials that are intended to be buried in soils
shall be protected from degradation under in-service conditions
to insure that their function shall not be impaired.
Comments:
Installer
should follow the manufacturer's installation instructions regarding
the method used to install buried components. Approved industry
methods and material must be used. Installations must also follow
local code requirements.
When
burying components, especially piping, the type of local soil
and its chemical reaction upon piping and insulation must be considered.
Figure 1 illustrates a ground mount of two ICS systems with buried
pipe and structural components.

Figure 1
Proceed
to the Next Transport Subsystem Guideline
Return
to the Transport Subsystem Main Page
|